• Juanicipio JV

JUANICIPIO PROJECT
Municipio Fresnillo Zacatecas, Mexico

MAG is an advanced stage development and exploration company, that is focused on the acquisition, development and exploration of high-grade, high-margin, district-scale projects located in the Americas.  MAG’s principal asset is a 44% interest in the Juanicipio project (the “Juanicipio Project”) located in Zacatecas state, Mexico, with Fresnillo plc (“Fresnillo”) owning the remaining 56% and the project Operator.  A processing facility is being constructed at the Juanicipio Project that is expected to commence commissioning in late Q4-2021, and the project is currently processing development material from the underground mine at an average nominal rate of 16,000 tonnes per month at a nearby processing plant (see Underground Mine Production - Juanicipio Project below).  MAG also has the right to earn a 100% interest in the Deer Trail Carbonate Replacement-Porphyry Project in central Utah, USA.

Juanicipio Project

MAG owns 44% of Minera Juanicipio S.A. de C.V. ("Minera Juanicipio"), an incorporated joint venture under the laws of Mexico, which owns the high-grade silver Juanicipio Project located in the Fresnillo District, Zacatecas State, Mexico. Fresnillo is the project Operator and holds the remaining 56% of Minera Juanicipio. The geology of the Juanicipio Project consists of high-grade silver-gold-lead-zinc epithermal vein deposits.  The principal vein, the Valdecañas Vein, has dilatant zones (bulges) at its east and west extremes and several en echelon vein splays and cross-veins– the term "Valdecañas Vein" is used to refer to this combined vein system. As shareholders of Minera Juanicipio, Fresnillo and MAG jointly approved project mine development on April 11, 2019, and project construction commenced immediately thereafter. In addition, exploration continues on both the Valdecañas Vein system and on other prospective targets within the joint venture property (see 'Juanicipio Project' below for a current project update).

The exploration and development of the Juanicipio Project are all being carried out by the project Operator, Fresnillo, with MAG participating in all board and technical committee meetings as well as ad-hoc meetings as required.  Construction of the processing plant is under the guidance of an Engineering, Procurement and Construction Management ("EPCM") contract entered into with an affiliate of Fresnillo. The Company's share of project costs is funded primarily by quarterly cash calls through its 44% interest in Minera Juanicipio, and to a lesser extent, incurred directly by MAG to cover expenses related to its own commissioned technical studies and analyses, as well as direct project oversight. Minera Juanicipio is governed by a shareholders' agreement and corporate by-laws, pursuant to which each shareholder is to provide funding pro-rata to its ownership interest, and if either party does not fund pro-rata, their ownership interest will be diluted in accordance with the shareholders' agreement.

In 2017, MAG commissioned AMC Mining Consultants (Canada) Ltd.  to prepare a Resource Estimate and Preliminary Economic Assessment for the Juanicipio Project (collectively, the "2017 PEA"), which was completed according to the NI 43-101 Standards of Disclosure for Mineral Projects and announced by the Company on November 7, 2017 (see Press Release of said date), with the MAG Silver Juanicipio NI 43-101 Technical Report (Amended and Restated) filed on SEDAR on January 19, 2018. 

The 2017 PEA incorporates major overall project upgrades over prior assessments, highlighted by the delineation and provision for mining of greatly expanded Indicated and Inferred Mineral Resources discovered in the Deep Zone, as defined in the 2017 PEA. The independent estimates of the Mineral Resources of the Juanicipio Project in the 2017 PEA were compiled using exploration data available up to December 31, 2016 and do not include the results of drilling programs undertaken since then (2017-2021) designed to further expand and infill the Deep Zone (see Exploration – Juanicipio Project below).  The volume of these new base metal-rich Deep Zone Mineral Resources identified in the 2017 PEA contributed to a significant expansion of project scope and enhancements to most aspects of the mine design. Truck haulage, shaft hoisting, and underground conveying, along with underground crushing of the mineralized rock are all projected to be utilized for delivering the mineralized material to the surface processing plant. As envisioned in the 2017 PEA, the proposed process plant has a planned production rate of 4,000 tpd, and will include a semi-autogenous grinding ("SAG")/ball mill comminution circuit followed by sequential flotation to produce a silver-rich lead concentrate, a zinc concentrate and a gold-rich pyrite concentrate. The plant and the associated tailings storage facilities are being built on open and flat joint venture owned land just north of the conveyor ramp portal.

Based on the 2017 PEA, MAG views the Juanicipio Project as a robust, high-grade, high-margin underground silver project exhibiting low development risks. While the results of the 2017 PEA are promising, by definition a Preliminary Economic Assessment is preliminary in nature and includes Inferred Mineral Resources that are considered too geologically speculative to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves.  Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability and there is no certainty that Mineral Resources will ever become Mineral Reserves.  There can therefore be no certainty that the results in the 2017 PEA will be realized. In addition, the 2017 PEA was commissioned independently by MAG, and not by Minera Juanicipio.  Fresnillo is the project operator and the actual development plan and timeline may be materially different from the scope, design and results envisaged in the 2017 PEA (see Juanicipio Project and Risks and Uncertainties below).

Highlights – March 31, 2021 & Subsequent to the Quarter End

(expressed in thousands of US dollars except as otherwise noted)

OPERATIONAL

  • Batch processing of mineralized material from development headings through the nearby Fresnillo plant continues at a targeted average nominal rate of 16,000 tonnes per month.
  • Since August 2020, 108,254 tonnes have been processed, expected to:
    • contribute cash-flow to offset some of the initial project capital; and
    • significantly speed up project ramp-up due to the de-risking of Juanicipio’s metallurgical performance.
  • As reported by the operator Fresnillo, the Juanicipio plant is expected to commence commissioning in Q4 2021, reaching 40 to 50% of its 4,000 tpd nameplate capacity by the end of 2021 and reaching 90 to 95% of its nameplate capacity in 2022.
  • During Q1 2021, on a 100% basis:
    • 36,395 tonnes of mineralized material processed through the Fresnillo plant;
    • 40% higher silver head grade (458 grams per tonne (“g/t”)) than the material processed in 2020 (328 g/t); and
    • 431,188 payable silver ounces, 631 payable gold ounces, 137 tonnes of lead and 199 tonnes of zinc sold.
  • Pre-commercial production sales of $10,085 (net of treatment and processing costs) on a 100% basis less $1,886 in mining and transportation costs, netting $8,199 that was recorded as gross profit by the Juanicipio Joint Venture in Q1 2021.
  • Positive progress was achieved during the quarter on the construction of the 4,000 tpd Juanicipio processing plant and civil works. Mechanical installation of the major processing equipment is nearly complete, and the construction is focused on completing the building envelope along with pipework and electrical/instrumentation installation.
  • Mechanical completion of the SAG and ball mills expected in Q2 2021.
  • Underground development at Juanicipio is now over 37 km (23 miles) with preparation of the first production stope complete.

EXPLORATION

  • In spite of temporary COVID-19 restrictions established by the Mexican Government in 2020, the full Juanicipio 2020 exploration program was completed as planned in 2020, drilling 33 holes and 27,900 metres. Full assays expected in Q2 2021.
  • The 2021 Exploration program for Juanicipio is budgeted at $6 million on a 100% basis, to be evenly allocated between continued step-out and infill drilling of the Valdecañas Vein System (including independent targeting of the Venadas Vein family and the Anticipada Vein) and three principal target areas elsewhere in the Joint Venture ground.
  • Deer Trail Project in Utah - Phase I drilling commenced in November, 2020 and is expected to be completed in Q2 2021 (assays and interpretations pending).

COVID-19

  • Juanicipio operator, Fresnillo, has implemented a range of safety measures and monitoring procedures, consistent with World Health Organization and Mexican Government COVID-19 directives.
  • In Q1 2021, Fresnillo, as operator, reported that commissioning of the Juanicipio processing plant is presently expected to commence in Q4 2021, a few months later than previously reported as some infrastructure contracts were delayed due to COVID-19 and COVID-19-related preventive measures implemented at site.

LIQUIDITY AND CAPITAL RESOURCES

  • As at March 31, 2021, MAG held cash and cash equivalents of $92,844 while Minera Juanicipio had cash on hand on a 100% basis of $3,067.

CORPORATE

  • Company continues to refresh its board, with the appointment of two new directors in Q1 2021:
  • Appointed Susan Mathieu on January 13, 2021. Ms. Mathieu has more than twenty-five years of international mining experience encompassing due diligence, exploration, project development, permitting, construction and operational positions. Her mining experience covers the full spectrum from mine-site to corporate leadership roles in governance, environment, sustainability, community, health and safety, compliance and risk management programs and strategies. Prior to joining the MAG board, Ms. Mathieu was the Vice President, Environment and Sustainability with NexGen Energy, and previously held senior positions with Placer Dome, Falconbridge, Centerra Gold and Golder Associates.
    • Appointed Tim Baker on March 31, 2021. Mr. Baker has substantial experience in operating international mines and projects. He was Executive Vice President and Chief Operating Officer of Kinross Gold Corporation prior to retiring in 2010. Prior to joining Kinross, he was with Placer Dome, where he held several key roles including Executive General Manager of Placer Dome Chile, Executive General Manager of Placer Dome Tanzania and Senior Vice President of the copper producing Compañia Minera Zaldivar. Mr. Baker is currently Chair of Golden Star Resources, a director of Sherritt International Corp. and serves on the Triple Flag Precious Metals Corp. Advisory Board. Mr. Baker has previously been a director on the boards of Augusta Resources Corp., Antofagasta PLC, Eldorado Gold Corp., Rye Patch Gold (later Alio Gold) and Pacific Rim Mining Corp.
    • At the time Tim Baker was appointed, Richard Clark resigned from the board to focus on other professional responsibilities.

JUANICIPIO PROJECT

Total Juanicipio Project expenditures incurred and capitalized directly by Minera Juanicipio (on a 100% basis) for Q1 2021 amounted to approximately $51,525 (Year 2020: $120,757). Of the total expenditures $50,354 (Year 2020: $115,937) are development expenditures and the remaining $1,171 (Year 2020: $4,820) are exploration expenditures. Gross profit (sales less cost of sales) from underground mine production for Q1 2021 totaled $8,199 (Q1 2020: N/A) on a 100% basis (see ‘Underground Mine Production – Juanicipio Project’ below).

UNDERGROUND MINE PRODUCTION – Juanicipio Project

Mineralized material from development is being batch processed, refined and sold on commercial terms at a targeted rate of 16,000 tonnes per month at the nearby Fresnillo plant twelve kilometres away. The resulting concentrate is treated in Torreon, Coahuila. This preproduction toll processing is expected to continue until the Juanicipio plant commences commissioning in Q4 2021 (see Processing Plant Construction and Commissioning below). The actual amount of material processed on a monthly basis may vary due to the variability of mineralization encountered in the development headings from month to month.

The first processing of mineralized development material commenced in August 2020, and through December 2020, a total of 71,859 tonnes of mineralized development material were processed. A further 36,395 tonnes were processed in Q1 2021 for a total of 108,254 tonnes to date, realizing commercial and operational de-risking opportunities for the joint venture.

The average silver head grade for the development material processed in Q1 2021 was 458 g/t (a 40% increase in silver head grade compared to the 328 g/t for development material processed in 2020). Total sales from the tonnes processed in Q1 2021, on a 100% basis, were 431,188 payable silver ounces, 631 payable gold ounces, 137 tonnes of lead and 199 tonnes of zinc. Provisional sales, net of processing and treatment costs totaled $10,085, and further costs incurred (including an applied mining cost and transportation costs) totaled $1,886 for a gross profit of $8,199 (see Table 1 below). The sales and treatment charges for tonnes processed in Q1 2021 were recorded on a provisional basis and will be adjusted based on final assay and pricing adjustments in accordance with the offtake contracts. Processing details are summarized in Table 1 below.

Table 1: Q1 2021 Development Material Processed at Fresnillo’s Processing Plant (100% basis)(expressed in thousands of US dollars except as otherwise noted)

  Quantity Average Per unit Amount Q1 2020 (1)
Silver (oz) (per oz) 431,188 ounces $25.87 $11,157 -
Gold (oz) (per oz) 631 ounces $1,728.59 $1,090 -
Lead (tonnes) (per lb) 137 tonnes $0.88 $ 267 -
Zinc (tonnes) (per lb) 199 tonnes $1.27 $ 555 -
Treatment and refining charges (“TCRC”) and other processing costs $(1,838) -
Provisional sales adjustment related to 2020 sales (2) $(1,146) -
Net Sales $10,085 -
Mining costs and transportation $(1,886) -
Gross Profit $8,199 -

(1) Underground mine production of development material commenced in August of 2020, so there are no comparable Q1 2020 results.
(2) Provisional sales for 2020 were finalized in Q1 2021 resulting in negative adjustment to net sales revenue of $1,146.

By bringing forward the start-up of the underground mine and processing mineralized development material at the Fresnillo plant, in advance of commissioning the Juanicipio plant, MAG and Fresnillo expect to secure several positive outcomes for the Juanicipio Project:

  • generating cash-flow from production to offset some of the cash requirements of the initial project capital;
  • de-risking the flotation process through a better understanding of the metallurgical characteristics and response of the Juanicipio mineralization;
  • increased certainty around the geological block model prior to start-up of the processing plant; and
  • allowing a faster and more certain ramp-up to the nameplate 4,000 tpd plant design.

PROCESSING PLANT CONSTRUCTION AND COMMISSIONING – Juanicipio Project

Construction plans for the 4,000 tpd processing plant commenced immediately after the formal project approval in April 2019. Basic engineering was completed during 2019 and, detailed engineering is now substantially complete. Development and construction of surface infrastructure facilities (power lines, access roads, auxiliary buildings, etc.) had already begun prior to the formal project approval in 2019 and is ongoing. In Q1 2021, further positive progress was achieved on the construction of the Juanicipio processing plant and civil works. The plant foundations were completed, with plant fabrication continuing. The SAG and ball mills are now installed, and their mechanical completion is expected in Q2 2021. The lead and zinc flotation cell lines have been installed and are being connected to the hydraulic circuit. Construction of the initial tailings storage facility has also begun.

Fresnillo, as operator, recently reported that commissioning of the Juanicipio processing plant is expected to commence in Q4 2021. The Juanicipio plant is expected to reach 40 to 50% of the nameplate 4,000 tpd capacity by the end of 2021 and 90-95% in 2022. In contrast, the 2017 PEA originally envisioned ramp-up to full production over 3 years after commissioning of the processing plant.

A regularly updated photo gallery of construction progress at Juanicipio is available at https://magsilver.com/projects/photo-gallery/#photo-gallery.

UNDERGROUND DEVELOPMENT – Juanicipio Project

Access to the mine is via twin underground declines that extend to the top of mineralization in the Valdecañas Vein. From the top of mineralization, the upper footwall haulage/access drift has been driven the length of the vein and three internal spiral production ramps are being extended from it to depth in the footwall of the mineralized envelope (vein). The three spiral ramps are situated behind the mineralized envelope to provide access to stopes within the vein and allow a planned mining rate of 4,000 tpd. Initial cross-cuts through the vein have been made from a number of points along the footwall ramps. Most expose well-mineralized vein and this initial development indicates that the grade and width of the mineralization is in line with previous drillcore-based estimates. As discussed above, the mineralized material encountered in these developments is being processed at the nearby Fresnillo processing plant (see Underground Mine Production above).

Mineralized material from mining of the vein will be conveyed to an underground crushing station (already excavated) and crushed underground. The crushed material will be trucked to the flotation plant until the conveyor is completed in 2022. When the conveyor is completed, the crushed mineralized material will be conveyed directly from the underground crushing station to the process plant area via a third ramp to the surface - the underground conveyor ramp. The conveyor ramp is approaching 71% completion and is being driven both from the surface and from the underground crushing chamber. This ramp will also provide access to the entire Valdecañas underground mining infrastructure and serve as a fresh air entry for the ventilation system. As well, the long-term mine ventilation system is nearing completion, with both main ventilation shafts completed and presently being linked up to the main ventilation level of the underground infrastructure.

Total underground development to date is now over 37 km (23 miles), including 2.6 km (1.6 miles) completed in the quarter ended March 31, 2021. Underground mine infrastructure is well advanced and development continues to focus on:

  • advancing the three internal spiral footwall ramps to be used to further access the full strike length of the Valdecañas Vein system;
  • making additional cross-cuts through the vein and establishing the initial mining stopes (preparation of the first production stope was concluded in the quarter ended September 30, 2020);
  • finalizing construction of the underground crushing system, underground warehouse, fuel storage and pumping station
  • advancing the underground conveyor ramp to and from the planned surface processing facility from both faces; and,
  • integrating additional ventilation and other associated underground infrastructure.

PROJECT CAPITAL (“CAPEX”) – Juanicipio Project

(expressed in thousands of US dollars except as otherwise noted)

In the first quarter of 2020, Fresnillo and MAG jointly announced an update to the initial capex required for the project (see Press Release dated February 24, 2020). The capex or pre-operative project capital cost on a 100% basis, as estimated from January 1, 2018 was revised to $440,000 from $395,000, to reflect additional expenditures incurred by Minera Juanicipio on the underground development and bringing forward the full construction costs for the life-of-mine ventilation shafts, as well as some sustaining capital to facilitate the early underground mine start.

The initial capital already expended from January 1, 2018 to March 31, 2021 is approximately $272,000 leaving an estimated $168,000 of remaining initial capital (MAG’s 44% estimated remaining share is $73,920 as at March 31, 2021). This remaining funding requirement will be reduced by both: existing cash held in Minera Juanicipio as at March 31, 2021 ($3,067 on a 100% basis); and, expected cash flows generated from mineralized development material processed at an average nominal rate of 16,000 tonnes per month through the Fresnillo processing plant until the Juanicipio plant is commissioned (see Underground Mine Production above and Liquidity and Capital Resources below).

EXPLORATION – Juanicipio Project

Most of the Juanicipio property remains unexplored with many untested exploration targets still to be pursued by the joint venture. Exploration drilling in recent years has been primarily designed to both convert the Inferred Mineral Resources included in the Deep Zone into Indicated Mineral Resources, and to further trace the Deep Zone laterally and to depth.

2020 Exploration Program

After a temporary COVID-19 exploration halt imposed by the Mexican Government in 2020, full exploration drilling at Juanicipio resumed in May of 2020 with five rigs, including three dedicated to Devico directional drilling. Drilling was focused on continued step-out and infill drilling of the Valdecañas Deep Zone. Holes were also directed at the Anticipada Vein and NE-trending Venadas Vein family targeting them independently from the Valdecañas Vein. Despite the temporary COVID-19 restriction noted, the full Juanicipio 2020 drilling program was completed as planned in 2020, comprising a total of 33 drill holes and 27,900 metres. Full assays are expected in Q2 2021.

An approved 2021 Juanicipio exploration program is currently in progress at Juanicipio (see Outlook below).

Quality Assurance and Control: The samples (half core) are shipped directly in security-sealed bags to ALS-Chemex Laboratories preparation facility in Guadalajara, Jalisco, Mexico (Certification ISO 9001). Samples shipped also include intermittent standards and blanks. Pulp samples are subsequently shipped to ALS-Chemex Laboratories in North Vancouver, Canada for analysis. Two extra pulp samples are also prepared and are analyzed (in progress) by SGS Laboratories (Certification ISO 9001) and Inspectorate Laboratories (Certification ISO 9001) (or another recognized lab). The remaining half core is placed back into the core boxes and is stored on site with the rest of the drill hole core in a secured core storage facility. The bulk reject is subsequently sent to the Center for Investigation and Technical Development ("CIDT") of Peñoles in Torreon, Coahuila State, Mexico for metallurgical testing where a fourth assay for each sample is analyzed and a calculated head grade is received on the basis of a concentrate balance. The CIDT also does a full microscopic, XRF and XRD mineralogical analysis.

COVID-19 – Juanicipio Project

The Juanicipio Project operator, Fresnillo, continues to closely monitor the spread of the virus and has implemented a range of safety measures in accordance with the World Health Organization and Mexican Government guidelines. These include stringent monitoring & hygiene, temperature screening and social distancing. Testing and contact tracing have been used to identify potential cases and prevent the spread of the virus. Fresnillo maintains an open dialogue with government officials at both the Federal and local level.

As noted above, according to Fresnillo the commissioning timetable was deferred a few months to Q4 2021 as some infrastructure contracts were delayed due to COVID-19 related restrictions as well as preventive measures put into place. The further impact of this pandemic could create or include significant COVID-19 specific costs, volatility in the prices for silver and other metals, further restrictions or temporary closures, additional travel restraints, supply chain disruptions and workforce interruptions, including loss of life. Depending on the duration and extent of the impact of COVID-19, this could materially impact the Company's financial performance, cash flows and financial position, and could result in material changes to the costs and time for the completion of development at Juanicipio. The total amount that the Company is required to finance in order to maintain its proportionate ownership in the project may increase from these and other consequences of the COVID-19 outbreak. See 'Virus outbreaks may create instability in work markets and may affect the Company's Business' in 'Risk and Uncertainties' below.

OUTLOOK

MAG's principal focus is the successful development of the Juanicipio Project and to further explore the Juanicipio property. The Company continually looks to enhance its project portfolio by evaluating new projects and through successful exploration of its current property holdings. However, MAG continues to execute its business plan prudently, with on-going project evaluations focusing primarily on potential high-grade, high-margin, district-scale opportunities.

Minera Juanicipio

Under the terms of an EPCM agreement, Fresnillo and its affiliates are overseeing the construction of the Juanicipio 4,000 tpd processing plant and associated surface and underground infrastructure. The Juanicipio processing plant is expected to commence commissioning in fourth quarter 2021 reaching 40 to 50% of nameplate capacity by the end of 2021 and achieving 90 to 95% of nameplate capacity in 2022. An Operator Services agreement has been finalized which will become effective upon initiation of commercial production. Both lead and zinc concentrate off-take agreements have been executed by Minera Juanicipio with Met-Mex Peñoles, S.A. De C.V., under which both concentrates are being treated at benchmark market terms in Torreón, Mexico.

During Q1 2021, further positive progress was made on construction of the flotation plant and other surface infrastructure. The plant foundations were completed with plant fabrication continuing. SAG and ball mills are now installed with their mechanical completion expected in Q2 2021. The lead and zinc flotation cell lines have been installed and are being connected to the hydraulic circuit. Underground development to date at Juanicipio is now over 37 km (23 miles) with access to the upper portion of the resource now achieved. Underground development priorities include continuing advance of the three internal spiral footwall production ramps designed to access the full strike length of the Valdecañas Vein system. Initial development indicates that the grade and width of the vein are in line with previous drilling-derived estimates, and preparation of the first production stope is complete.

Underground mine production from Juanicipio commenced in August 2020 ahead of the original schedule. Since then, 71,859 tonnes of mineralized development material with a silver head grade of 328 g/t were successfully processed through the Fresnillo plant through December 2020, and a further 36,395 tonnes processed in Q1 2021 (see Underground Mine Production above). Mineralized material from the mine is expected to be processed at a targeted average rate of 16,000 tonnes per month at the Fresnillo plant facility (100% owned by Fresnillo) until the Juanicipio plant is commissioned in Q4 2021. The actual amount of material processed on a monthly basis may vary due to the variability of mineralization encountered in the development headings from month to month. During April 2021, a further 16,771 tonnes of development material were processed.

The COVID-19 pandemic has had a material impact on the global economy, the scale and duration of which remain uncertain. The impact of this pandemic could include significant COVID-19 specific costs, volatility in the prices for silver and other metals, project development and mining restrictions or temporary closures, travel restraints, supply chain disruptions and workforce and contractor interruptions, including possible loss of life. These and other COVID-19 impacts could result in an increase in the total amount that the Company is required to finance in the project (see 'Virus outbreaks may create instability in work markets and may affect the Company's Business' in 'Risk and Uncertainties' below).

According to Fresnillo, the Juanicipio development is expected to create approximately 2,750 jobs during construction and 1,720 jobs once at full production, with potential to scale-up operations in the future beyond 4,000 tpd.

On the exploration front, the Juanicipio 2020 exploration program was completed as planned in 2020, comprising a total of 33 drill holes and 27,900 metres drilled. Full assays are expected in Q2 2021.

The 2021 Exploration program for Juanicipio is budgeted at $6 million, to be evenly allocated between continued step-out and infill drilling of the Valdecañas Vein System (including independent targeting of the Venadas Vein family and the Anticipada Vein) and three principal target areas elsewhere in the Joint Venture ground. Drilling of the Valdecañas Vein System began in January 2021 with four drill rigs (all assays pending), with a fifth expected mid-year depending on crew availability. Three of the drill rigs remain dedicated to Devico directional drilling. Permit applications for drilling the outlying targets have been submitted or are in the process of being generated pending surface access arrangements. Meanwhile, detailed mapping and sampling of these targets is underway. All aspects of the exploration work continue to be done under strict COVID-19 protocols.

You are now leaving the MAG Silver website to go to an external third-party website.

By selecting this link, you will be transferred to a website that is not affiliated with, or under the ownership or control of the MAG Silver site. Proceed at your own risk. We are not responsible or liable for the operation, content or policies of the website to which you are linking, and do not endorse, control, supervise or review its policies, assumptions, content or forward-looking statements. You should address any concerns or questions you may have regarding that website to the site Administrator or Webmaster of that website.

Fresnillo Annual Report 2019

You are now leaving the MAG Silver website to go to an external third-party website.

By selecting this link, you will be transferred to a website that is not affiliated with, or under the ownership or control of the MAG Silver site. Proceed at your own risk. We are not responsible or liable for the operation, content or policies of the website to which you are linking, and do not endorse, control, supervise or review its policies, assumptions, content or forward-looking statements. You should address any concerns or questions you may have regarding that website to the site Administrator or Webmaster of that website.

Website
Story of Juanicipio

It all began with gas station…

Story of Juanicipio

3D Video

Juanicipio JV

3D Video

Receive News & Email Updates


© 2021 MAG Silver Corp.
All rights reserved.
Disclaimer